1 Kanal House Construction Cost in Karachi

1 Kanal House Construction Cost in Karachi 2024

Building a house is a significant investment that requires meticulous planning, budgeting, and execution. In Karachi, constructing a 1 Kanal house involves various stages and components, each with its associated costs. This comprehensive guide breaks down the costs and provides insights into what it takes to build a 1 Kanal house in Karachi, ensuring you are well-prepared for your construction project.

Total Cost Overview

The total cost to construct a 1 Kanal house in Karachi is approximately 2.73 Crore PKR. This includes the costs for the grey structure, finishing materials, and labor. Here’s a quick breakdown:

  • Grey Structure Material Cost: 1.41 Crore PKR
  • Finishing Material Cost: 1.03 Crore PKR
  • Labor Cost: 28.29 Lakh PKR
  • Price Per Sq Ft: 4,327 PKR

Breakdown of Overall Construction Cost by Percentage (PKR)

  • Foundation & Structure: 1.49 Crore PKR
  • Plumbing Works: 15.51 Lakh PKR
  • Electrical Works: 20.66 Lakh PKR
  • Wood, Metal, and Tile Works: 78.94 Lakh PKR
  • Fittings & Fixtures: 8.06 Lakh PKR

Detailed Cost Breakdown

Foundation & Structure

The foundation and structure are the core elements of any building. This stage includes materials for the basic house structure, such as foundation, floors, walls, roofing, and plastering.

  • Total Cost: 1.49 Crore PKR
  • Bricks, Cement, Sand, & Crush: 95.39 Lakh PKR
    • Bricks + Rorhi: 26 PKR/Unit, Quantity: 197,122, Cost: 5,125,172 PKR
    • Cement: 1,278 PKR/Bag, Quantity: 2,120, Cost: 2,709,360 PKR
    • Sand: 85 PKR/Cft, Quantity: 10,598, Cost: 900,830 PKR
    • Crush: 150 PKR/Cft, Quantity: 5,355, Cost: 803,250 PKR
  • Roof Insulation, Termite & Water Proofing: 1.9 Lakh PKR
    • Roof Insulation: 249 PKR/Sft, Quantity: 454, Cost: 113,046 PKR
    • Termite Proofing: 1,700 PKR/Liter, Quantity: 15, Cost: 25,500 PKR
    • Water Proofing: 114 PKR/Sft, Quantity: 454, Cost: 51,756 PKR
  • Excavation & Steel Reinforcement: 28.83 Lakh PKR
    • Excavation & Backfill + Ghassu: 25 PKR/Cft, Quantity: 11,498, Cost: 287,450 PKR
    • Steel Reinforcement: 259,560 PKR/Tonne, Quantity: 10, Cost: 2,595,600 PKR
  • Labor Cost: 23.31 Lakh PKR

Plumbing Works

Plumbing works are crucial for water supply and drainage systems. This includes cold and hot water supply, insulation, drainage system piping, gas piping, pumps, and drains.

  • Total Cost: 15.51 Lakh PKR
  • Cold and Hot Water Supply: 1.59 Lakh PKR
    • Various pipes with respective rates and quantities.
  • Insulation Armaflex: 1.06 Lakh PKR
    • Insulation for different pipe diameters.
  • Drainage System Piping: 3.38 Lakh PKR
    • Pipes of various diameters with respective rates and quantities.
  • Gas Piping: 2.05 Lakh PKR
    • GI Welded Pipeline and Gas Cock.
  • Pumps and Drains: 3.38 Lakh PKR
    • Booster Pump, Submersible Water Transfer Pump, Floor Drains.
  • AC Drainage System: 46.75 Thousand PKR
  • UPVC Pipeline for Sewerage System: 1.13 Lakh PKR
  • Labor Cost: 2.46 Lakh PKR

Electrical Works

Electrical works involve underground wiring and installation of all electrical items, ensuring the house is well-lit and equipped with power outlets.

  • Total Cost: 20.66 Lakh PKR
  • Grey Structure: 3.72 Lakh PKR
  • Finishing: 16.94 Lakh PKR
  • Switches and Back Boxes: 2.28 Lakh PKR
    • Power Sockets, Fan Dimmer, Universal Switch Socket, etc.
  • Conduits & Accessories: 1.45 Lakh PKR
    • Electrical PVC Conduit with accessories.
  • Wires & Cables: 10.95 Lakh PKR
    • Various types of wires and cables for different applications.
  • Lights, Fans, and Chandeliers: 3.45 Lakh PKR
    • Various lights for different areas, ceiling fans, exhaust fans.
  • Labor Cost: 2.52 Lakh PKR

Wood, Metal, and Tile Works

This category includes cabinets, wardrobes, flooring, and all aluminum and iron works, which contribute significantly to the house’s aesthetic appeal and functionality.

  • Total Cost: 78.94 Lakh PKR
  • Paint and Ceiling Works: 17.72 Lakh PKR
    • False Ceiling: 130 PKR/Sft, Quantity: 1,890, Cost: 245,700 PKR
    • Paint: 57 PKR/Sft, Quantity: 26,775, Cost: 1,526,175 PKR
  • Tile Work: 41.48 Lakh PKR
    • Floor Tiles, Floor Skirting, Ceramic Tiles on Walls & Dado.
  • Wooden Doors: 6.77 Lakh PKR
    • Main Entrance Door, Room Doors, Washroom and Other Doors, Roof and Terrace Doors.
  • Windows: 2.58 Lakh PKR
    • Aluminum Room Windows, Aluminum Bathroom Windows.
  • Metal Works: 4.36 Lakh PKR
    • Staircase and Terrace Railing, Main Gate.
  • Wardrobes & Cabinets: 6.03 Lakh PKR
    • Wardrobes, Kitchen Cabinets.

Fittings & Fixtures

Fittings and fixtures include all the essential accessories required in the kitchen and bathrooms, making the house ready for occupation.

  • Total Cost: 8.06 Lakh PKR
  • Kitchen: 56.1 Thousand PKR
    • Kitchen Sink, Sink Mixer, Gully Trap Chamber.
  • Bathroom: 6.74 Lakh PKR
    • Water Closet, Vanity Basin, Basin Mixer, Muslim Shower, Shower Set, Toilet Paper Holder, Beveled Edge Mirror, Soap Dish.
  • Geyser & Manhole: 76.06 Thousand PKR
    • Geyser, Manhole.

Conclusion

Constructing a 1 Kanal house in Karachi is a significant undertaking that requires detailed planning and budgeting. The total estimated cost of 2.73 Crore PKR covers all aspects of construction, from the grey structure to the final finishing touches. By understanding the detailed breakdown of costs, homeowners can better manage their budget and ensure a successful construction project. Each component, from the foundation and structure to plumbing, electrical works, wood and tile works, and fittings and fixtures, plays a crucial role in creating a comfortable, functional, and aesthetically pleasing home.

Whether you are embarking on this construction journey for the first time or are experienced in building homes, having a comprehensive understanding of the costs and requirements will help you navigate the process more efficiently. Make sure to consult with professionals, adhere to local building codes, and prioritize quality materials to ensure your new home stands the test of time.

Frequently Asked Question

Wazir and Sons aims to be one of the best construction companies in Pakistan. We put all our determinations into our client’s work and tributes to be an inordinate service and construction company in Lahore.

While you’re planning for a new home, a constructed house is far more expensive than building the same house according to your own choice. However, Wazir and Sons offers you the market beating rates for both, whether you want to buy or you want to build your own customized dream home.

A small house approximately takes 2 to 3 months’ time. Our architects are experienced professionals who understand client’s demands and efficiently meet client’s potentials.

Wazir and Sons stands out in Lahore’s construction industry due to its unwavering commitment to quality, timely delivery, and client satisfaction. Our team’s expertise, attention to detail, and innovative approach make us a trusted choice for construction projects in Lahore.

When choosing construction companies in Pakistan, it’s crucial to consider factors such as experience, reputation, project portfolio, and compliance with quality standards. Look for companies with a proven track record and positive client feedback to ensure a successful project outcome.

Yes, with the efficient team effort, Wazir and Sons being the best construction company in Lahore feels proud to tell you that a house can be built in three months under the construction of our expert skills.

Wazir and Sons distinguishes itself through a combination of experience, innovation, and a dedicated team. Our focus on delivering exceptional quality in grey structure construction, timely project completion, and transparent communication with clients sets us apart. Choose Wazir and Sons for a seamless and reliable grey structure construction experience in Lahore.

Overseas Pakistanis trust Wazir and Sons because we never compromise on quality. We offer a 100-year guarantee on structural design and a comprehensive 5-year warranty, ensuring peace of mind for our clients. Our commitment to excellence and our track record of satisfied customers, especially among overseas Pakistanis, makes us their top choice.

Wazir and Sons has satisfied customers in various countries, including the United States, Dubai, Saudi Arabia, Gulf, United Arab Emirates, Germany, Australia, Canada, and several European nations. Our commitment to quality and our strong guarantees have earned us the trust of clients worldwide, especially among overseas Pakistanis residing in these regions.

A 1 kanal house in Pakistan requires around 1,600 bags of cement, at a cost of around PKR
23,88,000.
Other materials required for building a 1 kanal house include:
Kassu
A mixture of sand and mitti, used to fill empty plots and build the foundation. Around PKR 450,000 worth of Kassu is required.
Steel
Around 9 tons or 9,000 kg of 60 grade steel is required. &
You can use a house construction cost calculator to estimate the cost of building your home. You can enter the city, the area of the house, and the quality of materials you want to use.