3 Marla Grey Structure Cost in Lahore 2025

3 marla Grey structure cost in Lahore 2025

3 Marla Grey Structure Cost in Lahore 2025

In this blog we will discuss about 3 marla grey structure cost in 2025.

It costs total around 35.69Lac.

 

Plumbing Works=5.15 Lac

Plumbing works include underground piping and drainage systems materials.

 

AC Drainage System =8.86 Thousand

ITEM RATE QUANTITY COST
1″ dia Class “E” 108/Rft. 82 8,856

 

Cold and Hot Water Supply=30.3 Thousand

ITEM RATE QUANTITY COST
25 mm o/d Pipe 105/Rft. 122 12,810
32 mm o/d Pipe 172/Rft. 49 8,428
40 mm o/d Pipe 263/Rft. 12 3,156
50 mm o/d Pipe 394/Rft. 15 5,910

 

Drainage System Piping=41.49 Thousand

ITEM RATE QUANTITY COST
2″ Dia. Pipe 255/Rft. 49 12,495
3″ Dia. Pipe 343/Rft. 49 16,807
4″ Dia. Pipe 167/Rft. 73 12,191

 

Gas Piping=38.44 Thousand

ITEM RATE QUANTITY COST
GI Welded Pipeline 3/4” i/d 408/Rft. 91 37,128
Gas Cock 3/4″ i/d 1309/Unit 1 1,309

 

Insulation Armaflex=19.68 Thousand

ITEM RATE QUANTITY COST
32 mm o/d 443/Rft. 24 10,632
50 mm o/d 603/Rft. 15 9,045

 

Pumps and Drains=3.01 Lakh

ITEM RATE QUANTITY COST
Booster Pump 0.75 HP 151961/Unit 1 151,961
Submersible Water Transfer Pump 1 HP 142647/Unit 1 142,647
Floor Drains 1676/Unit 4 6,704

 

UPVC Pipeline for Sewerage System=21 Thousand

ITEM RATE QUANTITY COST
6″ dia Class “B” 700/Rft. 30 21,000

Electrical Works=1.03 Lac

 

Conduits & Accessories=31.58 Thousand

ITEM RATE QUANTITY COST
3/4” dia. Electrical PVC Conduit with accessories 29/Rft. 608 17,632
1” dia. Electrical PVC Conduit with accessories 30/Rft. 182 5,460
1.5” dia. Electrical PVC Conduit with accessories 40/Rft. 21 840
2” dia. Electrical PVC Conduit with accessories 49/Rft. 24 1,176
PVC Ceiling Fan Hook 539/Unit 12 6,468

 

Switches and Back Boxes=32.71 Thousand

ITEM RATE QUANTITY COST
Switch Boards 1363/Board 24 32,712

Foundation & Structure=29.51 Lac

 

Bricks, Cement, Sand, & Crush=19.14 Lakh

ITEM RATE QUANTITY COST
Bricks + Rorhi 27/Unit 33757 911,439
Cement 1350/Bag 363 490,050
Sand 195/Cft. 1815 353,925
Crush 154/Cft. 1033 159,082

 

Excavation & Steel Reinforcement=5.09 Lakh

ITEM RATE QUANTITY COST
Excavation & Backfill + Ghassu 22/Cft. 2217 48,774
Steel Reinforcement 230000/Tonne 2 460,000

 

Roof Insulation, Termite & Water Proofing=35.98 Thousand

ITEM RATE QUANTITY COST
Roof Insulation 244/Sft. 87 21,228
Termite Proofing 1668/Liter 3 5,004
Water Proofing 112/Sft. 87 9,744