Total cost is 82.15 Lac

  • Plumbing Works8.17 Lac
  • Electrical Works1.97 Lac
  • Foundation & Structure72.01 Lac

Plumbing Works=8.17 Lakh

AC Drainage System=20.95 Thousand

ITEM RATE QUANTITY COST
1″ dia Class “E” 108/Rft. 194 20,952

Cold and Hot Water Supply=71.73 Thousand

ITEM RATE QUANTITY COST
25 mm o/d Pipe 105/Rft. 287 30,135
32 mm o/d Pipe 172/Rft. 115 19,780
40 mm o/d Pipe 263/Rft. 29 7,627
50 mm o/d Pipe 394/Rft. 36 14,184

Drainage System Piping=97.49 Thousand

ITEM RATE QUANTITY COST
2″ Dia. Pipe 255/Rft. 115 29,325
3″ Dia. Pipe 343/Rft. 115 39,445
4″ Dia. Pipe 167/Rft. 172 28,724

Gas Piping=91.65 Thousand

ITEM RATE QUANTITY COST
GI Welded Pipeline 3/4” i/d 408/Rft. 215 87,720
Gas Cock 3/4″ i/d 1309/Unit 3 3,927

Insulation Armaflex=46.96 Thousand

ITEM RATE QUANTITY COST
32 mm o/d 443/Rft. 57 25,251
50 mm o/d 603/Rft. 36 21,708

Pumps and Drains=3.11 Lakh

ITEM RATE QUANTITY COST
Booster Pump 0.75 HP 151961/Unit 1 151,961
Submersible Water Transfer Pump 1 HP 142647/Unit 1 142,647
Floor Drains 1676/Unit 10 16,760

UPVC Pipeline for Sewerage System=50.4 Thousand

ITEM RATE QUANTITY COST
6″ dia Class “B” 700/Rft. 72 50,400

Electrical Works=1.97 Lakh

Conduits & Accessories=66.85 Thousand

ITEM RATE QUANTITY COST
3/4” dia. Electrical PVC Conduit with accessories 29/Rft. 1435 41,615
1” dia. Electrical PVC Conduit with accessories 30/Rft. 430 12,900
1.5” dia. Electrical PVC Conduit with accessories 40/Rft. 50 2,000
2” dia. Electrical PVC Conduit with accessories 49/Rft. 57 2,793
PVC Ceiling Fan Hook 539/Unit 14 7,546

Switches and Back Boxes=38.16 Thousand

ITEM RATE QUANTITY COST
Switch Boards 1363/Board 28 38,164

Foundation & Structure=72.01 Lakh

Bricks, Cement, Sand, & Crush=46.88 Lakh

ITEM RATE QUANTITY COST
Bricks + Rorhi 27/Unit 82932 2,239,164
Cement 1350/Bag 892 1,204,200
Sand 195/Cft. 4459 869,505
Crush 154/Cft. 2439 375,606

Excavation & Steel Reinforcement=12.65 Lakh

ITEM RATE QUANTITY COST
Excavation & Backfill + Ghassu 22/Cft. 5236 115,192
Steel Reinforcement 230000/Tonne 5 1,150,000

Roof Insulation, Termite & Water Proofing=85.37 Thousand

ITEM RATE QUANTITY COST
Roof Insulation 244/Sft. 207 50,508
Termite Proofing 1668/Liter 7 11,676